SlideShare a Scribd company logo
1 of 56
Download to read offline
Board Meeting
                    September 29, 2010




Timothy P. Cahill                        Katherine P. Craven
Chairman, State Treasurer                 Executive Director
Savings from MSBA Process
                    Not including Bid Savings




Timothy P. Cahill                               Katherine P. Craven
Chairman, State Treasurer                        Executive Director
MSBA Visits
   Since the July Board the MSBA has visited 43 Districts
                                                                    Check Presentations/
   Project Visits                                                    Ground Breakings


    Foxborough           Belmont                   Springfield       Whitman-Hanson
      Littleton           Malden                    Plymouth             Woburn
      Taunton          New Bedford                   Beverly            Sturbridge
      Ashland           Hingham                    Dartmouth        Hampden-Wilbraham
     Wellesley          Middleton                    Taunton             Revere
     Haverhill          Norwood                     Rochester
     Rockport             Florida                    Hanover
     Braintree            Revere                    Attleboro
       Quincy          Marblehead                    Bedford
       Sharon           Worcester                Great Barrington
      Woburn             Danvers                    Nashoba
   North Attleboro       Woburn                     Brockton
                     Hamilton-Wenham                 Palmer



September 29, 2010   The Massachusetts School Building Authority                        3
                              www.massschoolbuildings.org
Summary of Bid Data
                                 Number of Design Basis for Project                                          Construction
                       Year       Projects   Enrollment      Budget                                             Budget
                            2009          11          8,188 $205.6 M                                           $171.5 M
                            2010          38        30,354 $1.62 B                                              $1.26 B
                            2011           9          9,270 $471.3 M                                          $362.8 M

               Grand Total                              58                    47,812        $2.30 B               $1.66 B
         Note: These numbers are based on preliminary information received from the District and are subject to further review and calculation.


•       Of the 38 projects scheduled to bid in 2010, 22 bids have been received.
•       To date, the bid savings for the 2010 projects is $100.3 million with potential grant
        savings of $57.2 million.
•       Sixteen projects still to be bid or GMPs finalized in 2010 with an estimated construction
        cost over $636 million
•       Bids received in September: Billerica, Natick, and Wayland
•       Anticipated Bids:
               October - Brookline, Norfolk, Danvers, Tewksbury and Dedham
             November - Shawsheen
             December - Southbridge, Grafton, Rockland, South Shore RVT,
                          Marshfield, and Needham
    September 29, 2010                      The Massachusetts School Building Authority                                                           4
                                                           www.massschoolbuildings.org
Project Estimate vs. 2010 Bid Amount




     Note: These numbers are based on preliminary information received from the District and are subject to further review and calculation.

September 29, 2010                      The Massachusetts School Building Authority                                                           5
                                                       www.massschoolbuildings.org
Project Estimate vs. 2009 Bid Amount




     Note: These numbers are based on preliminary information received from the District and are subject to further review and calculation.

September 29, 2010                      The Massachusetts School Building Authority                                                           6
                                                       www.massschoolbuildings.org
Design Development / Construction Phases
    Ongoing Scope, Budget & Schedule Monitoring

•   Total of 64 Projects: Construction Total approx $ 2.21 billion

•   22 Projects in Design Development
     – Estimated Construction Cost of $842,747,641

•   29 Projects in Construction
     – Construction Cost of $1,077,265,624

•   13 Projects Completed for 2010 Occupancy
     – Construction Cost of $292,054,139

•   19 Additional Projects for Consideration Today
     – Estimated Construction Cost of $178,966,011



September 29, 2010   The Massachusetts School Building Authority     7
                              www.massschoolbuildings.org
Design Development / Construction Phases
   Ongoing Scope, Budget & Schedule Monitoring




September 29, 2010   The Massachusetts School Building Authority   8
                              www.massschoolbuildings.org
Design Development / Construction Phases
   Ongoing Scope, Budget & Schedule Monitoring




         Design Development Phase

                Review Submittals
      for Design Development, 60% and 90%

      Review Bid Amounts and Adjust Grant
               Amount as Needed

     Track Construction Budget Throughout
    Design Process Using MSBA Cost Estimate
            Comparison Spreadsheet


    Scope and Budget Fixed Upon Execution of
                   the PFA


September 29, 2010        The Massachusetts School Building Authority   9
                                     www.massschoolbuildings.org
Cost Estimate Comparison Spreadsheet




September 29, 2010   The Massachusetts School Building Authority   10
                              www.massschoolbuildings.org
Design Development / Construction Phases
   Ongoing Scope, Budget & Schedule Monitoring
              Construction Phase

           Review OPM Monthly Reports

       Bi-Monthly Site Visits & Project Status
                     Meetings

     Assess Eligibility of CO’s Including Owner
                      Directives

         Review Reimbursement Requests

          Design Development Phase

                Review Submittals
      for Design Development, 60% and 90%

      Review Bid Amounts and Adjust Grant
               Amount as Needed

     Track Construction Budget Throughout
    Design Process Using MSBA Cost Estimate
            Comparison Spreadsheet

    Scope and Budget Fixed Upon Execution of
                   the PFA


September 29, 2010           The Massachusetts School Building Authority   11
                                         www.massschoolbuildings.org
Budget Revision Request Form
                   Excerpts




September 29, 2010   The Massachusetts School Building Authority   12
                              www.massschoolbuildings.org
Vote to Move to Feasibility Study

Region     District Name             School Name              Grades Served          Status                     Recommendation


                               Monument Mountain Regional                                              Feasibility Study, subject to intensive
  1         Berkshire Hills                                       9-12        Feasibility Invitation
                                     High School                                                         pre-feasibility scoping agreement

                                                                                                       Feasibility Study, subject to intensive
  4        Concord-Carlisle    Concord-Carlisle High School       9-12        Feasibility Invitation
                                                                                                         pre-feasibility scoping agreement

                                  Greater New Bedford                                                  Feasibility Study, subject to intensive
  6      Greater New Bedford                                      9-12        Feasibility Invitation
                               Vocational Technical School                                               pre-feasibility scoping agreement




September 29, 2010                 The Massachusetts School Building Authority                                                            13
                                                  www.massschoolbuildings.org
Green Repair Update




September 29, 2010    The Massachusetts School Building Authority   14
                               www.massschoolbuildings.org
Green Repair Program: FY 11 SOI Intake
                                                                                                     200

                                                                                          190
  • Green Repair SOI opened August 11, 2010
                                                                                                     180
  • First SOI submitted on September 2, 2010
  • Green Repair SOI process closed September 22, 2010                                               160

  • Approximately 190 SOIs under review
                                                                                                     140
  • More than 95 Districts filed SOIs
  • 74% SOIs submitted three days before deadline                                                    120




                                                                                                           # of SOI
  • 49% SOIs submitted on deadline
                                                                                                     100


                                                                                                     80
                                                Daily Submissions
                                                Cumulative Submissions                               60


                                                                                                     40


                                                                                                     20


                                                                                                      0
                                                                         Submittal Date
         11-Aug        18-Aug        25-Aug        1-Sep         8-Sep           15-Sep         22-Sep


September 29, 2010              The Massachusetts School Building Authority                                           15
                                          www.massschoolbuildings.org
Green Repair Program Status
• 39 Districts are currently in the Green Repair Program.

• 12 Districts representing 23 schools were invited to
  participate in the Green Repair Program by the MSBA’s
  Board of Directors on May 26, 2010.
     – Of these 12 Districts, 8 have selected Owner’s Project Managers
     – Of these 12 Districts, 7 have selected Designers

• At today’s Board meeting, MSBA staff have
  recommended 7 districts representing 13 schools for
  Project Funding Agreements totaling $9,806,692 in Total
  Project Budgets and approximately $5,992,870 in MSBA
  grants.

September 29, 2010   The Massachusetts School Building Authority    16
                              www.massschoolbuildings.org
Invitation to Green Repair Program




September 29, 2010   The Massachusetts School Building Authority   17
                              www.massschoolbuildings.org
Green Repair Program
              Authorization to Execute Project Funding
                             Agreement
Vote - Project Funding Agreement                                                           Total: $ 9,806,692 $       9,620,646                    $    5,992,870

                                                                                                                                                   Approximate
                                           Age of                                                  District Total MSBA Total
                                                                                                                                                   Total Grant
                                          Existing            2009/10 Existing                        Project     Facility Grant   Reimbursement
                                                                                                                                                    Amount
  District             School             Building    Grade    Enroll Sq.Ft.     Project Scope        Budget          Basis            Rate
                                                                                 Project Funding
Acton        CT Douglas Elementary         1965        K-6     499     46,300                      $   471,699 $        471,699       43.85%           $206,840
                                                                                   Agreement
                                                                                 Project Funding
             Attleboro High                1961        9-12    1,756   428,700                     $   499,328 $        499,328       57.74%           $288,312
                                                                                   Agreement
                                                                                 Project Funding
             Hill Roberts Elementary       1975        K-4     475     76,630                      $   880,000 $        880,000       57.74%           $508,112
                                                                                   Agreement
Attleboro
                                                                                 Project Funding
             Hyman Fine Elementary         1975        K-4     429     76,630                      $   880,000 $        880,000       57.74%           $508,112
                                                                                   Agreement
                                                                                 Project Funding
             Studley Elementary            1965        K-4     432     71,000                      $ 1,187,500 $      1,187,500       57.74%           $685,663
                                                                                   Agreement
                                                                                 Project Funding
Conway       Conway Grammar School         1991        PK-6    175     31,000                      $ 1,353,450 $      1,167,404       54.36%           $634,601
                                                                                   Agreement
             Goodrich School (Fitchburg                                          Project Funding
                                           1891        9-12    139     14,400                      $   422,714 $        422,714       80.00%           $338,171
             Alternative High School)                                              Agreement
             Memorial Intermediate                                               Project Funding
                                           1967         5-8    662     126,800                     $ 1,177,532 $      1,177,532       80.00%           $942,026
             School                                                                Agreement
Fitchburg
             Reingold Elementary                                                 Project Funding
                                           1969        K-4     574     75,900                      $    698,333 $       698,333       80.00%           $558,667
             School                                                                Agreement
             South Street Elementary                                             Project Funding
                                           1963        PK-4    650     202,600                     $    701,186 $       701,186       80.00%           $560,949
             School                                                                Agreement
                                                                                 Project Funding
Hancock      Hancock Elementary            1958        PK-6     41      6,800                      $    277,450 $       277,450       45.32%           $125,740
                                                                                   Agreement
           Rockport Elementary                                                   Project Funding
Rockport                                   1953        PK-5    400     65,307                      $   687,500   $      687,500       41.10%           $282,563
           School                                                                  Agreement
           Toy Town Elementary                                                   Project Funding
Winchendon                                 1963         3-5    389     116,000                     $    570,000 $       570,000       61.95%           $353,115
           School                                                                  Agreement

         September 29, 2010                          The Massachusetts School Building Authority                                                        18
                                                               www.massschoolbuildings.org
Recommendation to Move to Project
                      Scope & Budget
Vote - Project Scope and Budget                                                                              Total: $ 217,747,744    $ 190,388,424                       $ 121,637,682
                                Age of                                                    Proposed                                     MSBA Total                          Approximate
                               Existing                    2009/10 Projected   Existing    Square      Preferred      District Total  Facility Grant Reimbursement         Total Grant
  District      School         Building        Grade        Enroll   Enroll     Sq.Ft.     Footage    Schematic     Project Budget       Basis               Rate            Amount
 Adams-      Hoosac Valley                  current 7-12                                                                                                    77.37%,
                                1969                        808       805      158,126    173,999      Add/Reno        $40,561,257    $36,038,192                         $28,243,131**
 Cheshire        HS                       proposed 6-12                                                                                                    78.37%*
                                          Closed in 2009                                             Note: SOI school, however proposed solution is for the MS to remain closed and to
               Adams MS         1952                         0         0       68,000        0
                                          Students in HS                                             house students in renovated HS
               Jr./Sr. High                 current 7-12    551       630                                                                                 62.52%,
  Granby                        1960                                           86,800     133,896        New          $45,965,516      $44,562,943                      $28,306,382**
                 School                   proposed 6-12    (7-12)    (6-12)                                                                               63.52%*
                                            current 9-12    323
 Maynard      High School       1962                                  410      82,947     121,100        New          $45,769,442      $42,280,580        56.42%         $23,854,703
                                          proposed 8-12    (9-12)

 Medway      Middle School      1960           5-8          842       800      223,780    216,820       Repair        $22,116,566      $20,850,314        50.79%         $10,589,875

 Norfolk
              High School       1917          9-12          468       550      114,816    102,097      Add/Reno       $28,552,385      $27,564,046        55.76%         $15,369,712
County Agr
             East Somerville               current 1-8       546
Somerville                      1972                                  500      118,500    121,100      Add/Reno       $34,782,578      $19,092,349        80.00%         $15,273,879
               Community                  proposed K-8      (1-8)



        *Contingent upon approval from the Office of the Inspector General to utilize CM-at-Risk construction delivery method
        **Approximate Total Grant Amount reflects the higher reimbursement rate.




        September 29, 2010                               The Massachusetts School Building Authority                                                                    19
                                                                        www.massschoolbuildings.org
Adams-Cheshire – Hoosac Valley
            Middle/High School
•    Built in 1969
•    Addition/Renovation: 173,999 sf
•    Grades: 6-12
•    Category: Project Scope & Budget
•    District Total Project Budget: $40,561,257
•    Basis of Maximum Grant Amount: $36,038,192
•    Reimbursement Rate: 77.37%, 78.37%*
•    MSBA Maximum Grant Amount: $28,243,131**
•    Town Meeting Vote: October 18, 2010
•    Special Ballot Vote: October 18, 2010
*Contingent upon approval from the Office of the Inspector General to utilize CM-at-Risk construction delivery method.
**Based on reimbursement rate of 78.37%

September 29, 2010               The Massachusetts School Building Authority                                        20
                                             www.massschoolbuildings.org
Hoosac Valley Middle/High School




September 29, 2010   The Massachusetts School Building Authority   21
                              www.massschoolbuildings.org
Hoosac Valley Middle/High School




September 29, 2010   The Massachusetts School Building Authority   22
                              www.massschoolbuildings.org
Hoosac Valley Middle/High School




September 29, 2010   The Massachusetts School Building Authority   23
                              www.massschoolbuildings.org
Granby Middle / High School
•    Built in 1960
•    New Construction: 133,896 sf
•    Grades: current 7-12, proposed 6-12
•    Category: Project Scope & Budget
•    District Total Project Budget: $45,965,516
•    Basis of Maximum Grant Amount: $44,562,943
•    Reimbursement Rate: 62.52%, 63.52%*
•    MSBA Maximum Grant Amount: $28,306,382**
•    Town Meeting Vote: October 18, 2010
•    Special Ballot Vote: November 2, 2010
*Contingent upon approval from the Office of the Inspector General to utilize CM-at-Risk construction delivery method.
**Based on reimbursement rate of 63.52%


September 29, 2010               The Massachusetts School Building Authority                                        24
                                             www.massschoolbuildings.org
Granby Middle / High School




September 29, 2010   The Massachusetts School Building Authority   25
                              www.massschoolbuildings.org
Granby Middle / High School




September 29, 2010   The Massachusetts School Building Authority   26
                              www.massschoolbuildings.org
Granby Middle / High School




September 29, 2010   The Massachusetts School Building Authority   27
                              www.massschoolbuildings.org
Maynard High School
•   Built in 1962
•   New Construction: 121,100 sf
•   Grades: current 9-12, proposed 8-12
•   Category: Project Scope & Budget
•   District Total Project Budget: $45,769,442
•   Basis of Maximum Grant Amount: $42,280,580
•   Reimbursement Rate: 56.42%
•   MSBA Maximum Grant Amount: $23,854,703
•   Town Meeting Vote: October 25, 2010
•   Special Ballot Vote: December 2, 2010


September 29, 2010     The Massachusetts School Building Authority   28
                                www.massschoolbuildings.org
Maynard High School




September 29, 2010     The Massachusetts School Building Authority   29
                                www.massschoolbuildings.org
Maynard High School




September 29, 2010    The Massachusetts School Building Authority   30
                               www.massschoolbuildings.org
Maynard High School




September 29, 2010    The Massachusetts School Building Authority   31
                               www.massschoolbuildings.org
Maynard High School




September 29, 2010     The Massachusetts School Building Authority   32
                                www.massschoolbuildings.org
Medway Middle School
•   Built in 1960
•   Repair: 216,820 sf (excludes central admin)
•   Grades: 5-8
•   Category: Project Scope & Budget
•   District Total Project Budget: $22,116,566
•   Basis of Maximum Grant Amount: $20,850,314
•   Reimbursement Rate: 50.79%
•   MSBA Maximum Grant Amount: $10,589,875
•   Town Meeting Vote: November 15, 2010
•   Special Ballot Vote: Based on Town Vote,
                           1st Week of December

September 29, 2010   The Massachusetts School Building Authority   33
                              www.massschoolbuildings.org
Medway Middle School




September 29, 2010   The Massachusetts School Building Authority   34
                              www.massschoolbuildings.org
Medway Middle School




September 29, 2010   The Massachusetts School Building Authority   35
                              www.massschoolbuildings.org
Norfolk County Agricultural High School
•   Built in 1917
•   Addition/Renovation: 102,097 sf
•   Grades: 9-12
•   Category: Project Scope & Budget
•   District Total Project Budget: $28,552,385
•   Basis of Maximum Grant Amount: $27,564,046
•   Reimbursement Rate: 55.76%
•   MSBA Maximum Grant Amount: $15,369,712
•   Vote: October 13, 2010
•   Vote: January 30, 2011


September 29, 2010   The Massachusetts School Building Authority   36
                              www.massschoolbuildings.org
Norfolk County Agricultural High School




September 29, 2010   The Massachusetts School Building Authority   37
                              www.massschoolbuildings.org
Norfolk County Agricultural High School




   Agricultural Mechanics Building


September 29, 2010          The Massachusetts School Building Authority   38
                                     www.massschoolbuildings.org
Norfolk County Agricultural High School




                                                            Agricultural Mechanics Building

September 29, 2010   The Massachusetts School Building Authority                              39
                              www.massschoolbuildings.org
Norfolk County Agricultural High School




                                                        Animal Sciences Building

September 29, 2010   The Massachusetts School Building Authority                   40
                              www.massschoolbuildings.org
Norfolk County Agricultural High School




Animal Science Building




September 29, 2010        The Massachusetts School Building Authority   41
                                   www.massschoolbuildings.org
Norfolk County Agricultural High School




   Annex Building

September 29, 2010   The Massachusetts School Building Authority   42
                              www.massschoolbuildings.org
Norfolk County Agricultural High School




   Horse Barn


September 29, 2010   The Massachusetts School Building Authority   43
                              www.massschoolbuildings.org
Somerville: East Somerville Community
                School
•   Built in 1972
•   Addition/Renovation: 121,100 sf
•   Grades: current 1-8, proposed K-8
•   Category: Project Scope & Budget
•   District Total Project Budget: $34,782,578
•   Basis of Maximum Grant Amount: $19,092,349
•   Reimbursement Rate: 80.00%
•   MSBA Maximum Grant Amount: $15,273,879
•   City Meeting Vote: TBD
•   Special Ballot Vote: TBD


September 29, 2010   The Massachusetts School Building Authority   44
                              www.massschoolbuildings.org
Somerville: East Somerville Community
                School




September 29, 2010   The Massachusetts School Building Authority   45
                              www.massschoolbuildings.org
Somerville: East Somerville Community
                School




September 29, 2010   The Massachusetts School Building Authority   46
                              www.massschoolbuildings.org
Somerville: East Somerville Community
                School




September 29, 2010   The Massachusetts School Building Authority   47
                              www.massschoolbuildings.org
2010 Needs Survey
• Assessments
    – Approximately 1775 Schools
    – 327 School Districts
• Data Accuracy
    – 8-week intensive QA
         • 20% sampling of school surveys
         • Queries to identify data that fell outside normal
           ranges
         • Follow-up visits to confirm data
    – Superintendent’s review
September 29, 2010    The Massachusetts School Building Authority   48
                               www.massschoolbuildings.org
2010 Needs Survey
• Scoring Methodology – Three Ratings
     – Building Conditions
        • Assessment of 7 site and 18 building systems
        • 1 to 4 Scale – Analogous to 2006 rating
     – General Physical Environment
        • Evaluation of conditions that affect the physical
          learning environment
        • 1 to 4 Scale
     – Space Utilization
        • How space is used compared to the average
        • Above Average, Average, Below Average

September 29, 2010    The Massachusetts School Building Authority   49
                               www.massschoolbuildings.org
2010 Needs Survey
• Condition of Massachusetts schools is
  good.
     – 80% received Building Conditions rating of 1
       or 2.
     – Less than 2% received Building Conditions
       rating of 4.
     – 62 schools received rating of 4 in 2006.
          • 9 received funding
          • 19 in Capital Pipeline
          • 6 Closed

September 29, 2010    The Massachusetts School Building Authority   50
                               www.massschoolbuildings.org
2010 Needs Survey
• General Environment – Factors in Analysis
     – Daylighting
     – Classroom Size
     – Open Floor Plan
• More than 90% of schools received a
  rating of 1 or 2
• Only 2% received a rating of 4.


September 29, 2010    The Massachusetts School Building Authority   51
                               www.massschoolbuildings.org
2010 Needs Survey
• Space Utilization – Factors in Analysis
     – GSF per student
     – Students per classroom
     – Temporary or non-traditional classrooms
     – Classroom size
• Nearly 23% of schools received a Below
  Average rating
• Less than 8% earned an Above Average
  rating
September 29, 2010    The Massachusetts School Building Authority   52
                               www.massschoolbuildings.org
2010 Needs Survey
• Space Utilization
     – Since 2006 more than 80 schools have closed
       or consolidated
          • Region 6 – 36 school closures
     – More than 1,300 unused classrooms
          • Over 1 million square feet being used for storage,
            district administration, municipal organizations or
            private entities



September 29, 2010    The Massachusetts School Building Authority   53
                               www.massschoolbuildings.org
2010 Needs Survey
• Maintenance
   – General Cleanliness
   – Routine Systems Maintenance
   – Capital Repair
• 74% of schools were rated average in all categories.
• Only 2% of schools received Above Average ratings
  in all areas
• 12 schools were Below Average across the board
• No relationship between maintenance and
  community wealth

September 29, 2010    The Massachusetts School Building Authority   54
                               www.massschoolbuildings.org
Project Status Report
                                                    Feasibility
                                                     Study /
                                   Local            Schematic           Design
                      Total      Clearance           Design           Development   Construction

New Program             123               35                     45          21             24


Waitlist                 13                                       2                         11


Green Repair             39               12                     17           1              7

Closeout/
Audit                    11
Complete

Total                   186               47                     64          22             42

 September 29, 2010       The Massachusetts School Building Authority                       55
                                   www.massschoolbuildings.org
Project Status Report
• Enrollment
   – 2 enrollments completed this period
   – 9 certifications pending
   – Enrollments complete for projects for 66,000 students
• Owner’s Project Manager
   – 8 districts completed OPM procurement
   – Over $57 million in OPM fees to date
• Designer Selection Panel
   – 2 districts participated in DSP – 1 selection, 1 scheduled for interviews
   – 4 districts scheduled for DSP in October/November
   – Over $143 million in Designer fees
• Commissioning
   – 2 Commissioning consultant contracts executed for $408,000
   – Over $5 million in consultant contracts to date

  September 29, 2010     The Massachusetts School Building Authority     56
                                  www.massschoolbuildings.org

More Related Content

Similar to September Board meeting presentation

Peachtree City Huddleston Road Redevelopment Project
Peachtree City Huddleston Road Redevelopment ProjectPeachtree City Huddleston Road Redevelopment Project
Peachtree City Huddleston Road Redevelopment ProjectKwame Som-Pimpong
 
K-7-Corridor-Study-Final-Report_01
K-7-Corridor-Study-Final-Report_01K-7-Corridor-Study-Final-Report_01
K-7-Corridor-Study-Final-Report_01Andrea Hutchins
 
Item # 7 - 2022 Street Maintenance Program
Item # 7 - 2022 Street Maintenance ProgramItem # 7 - 2022 Street Maintenance Program
Item # 7 - 2022 Street Maintenance Programahcitycouncil
 
Simin Rasolee Resume 4-17-2015 version 2
Simin Rasolee Resume 4-17-2015 version 2 Simin Rasolee Resume 4-17-2015 version 2
Simin Rasolee Resume 4-17-2015 version 2 Simin Rasolee
 
Chicago Infrastructure Trust Briefing
Chicago Infrastructure Trust BriefingChicago Infrastructure Trust Briefing
Chicago Infrastructure Trust BriefingTom Tresser
 
Dumbarton Crossbay
Dumbarton Crossbay Dumbarton Crossbay
Dumbarton Crossbay Adina Levin
 
Property Tax Assessment Financing
Property Tax Assessment FinancingProperty Tax Assessment Financing
Property Tax Assessment Financingbrunogobeil
 
Crawfordville Town Plan Draft Report Chamber
Crawfordville Town Plan Draft Report ChamberCrawfordville Town Plan Draft Report Chamber
Crawfordville Town Plan Draft Report ChamberChuck Robinson
 
Single Conversation Slides 15th June 2010
Single Conversation Slides   15th June 2010Single Conversation Slides   15th June 2010
Single Conversation Slides 15th June 2010jelutharas
 
Broadway corridor-planning-program-presentation-may-2018
Broadway corridor-planning-program-presentation-may-2018Broadway corridor-planning-program-presentation-may-2018
Broadway corridor-planning-program-presentation-may-2018Kathryn Huang
 
Secrets of a Successful Land Development Approval Process
Secrets of a Successful Land Development Approval ProcessSecrets of a Successful Land Development Approval Process
Secrets of a Successful Land Development Approval Processkevin_riles
 
APWA Florida Proj Award_UEP
APWA Florida Proj Award_UEPAPWA Florida Proj Award_UEP
APWA Florida Proj Award_UEPPhilip Tunnah
 
Built operate transfer case studies in local construction Sector in Pakistan
Built operate transfer case studies in local construction Sector in PakistanBuilt operate transfer case studies in local construction Sector in Pakistan
Built operate transfer case studies in local construction Sector in PakistanMeesum Zaidi
 

Similar to September Board meeting presentation (20)

Peachtree City Huddleston Road Redevelopment Project
Peachtree City Huddleston Road Redevelopment ProjectPeachtree City Huddleston Road Redevelopment Project
Peachtree City Huddleston Road Redevelopment Project
 
January 2010 Presentation to MMA Conference
January 2010 Presentation to MMA ConferenceJanuary 2010 Presentation to MMA Conference
January 2010 Presentation to MMA Conference
 
January 2010 MA Municipal Association Presentation
January 2010 MA Municipal Association PresentationJanuary 2010 MA Municipal Association Presentation
January 2010 MA Municipal Association Presentation
 
K-7-Corridor-Study-Final-Report_01
K-7-Corridor-Study-Final-Report_01K-7-Corridor-Study-Final-Report_01
K-7-Corridor-Study-Final-Report_01
 
Item # 7 - 2022 Street Maintenance Program
Item # 7 - 2022 Street Maintenance ProgramItem # 7 - 2022 Street Maintenance Program
Item # 7 - 2022 Street Maintenance Program
 
Simin Rasolee Resume 4-17-2015 version 2
Simin Rasolee Resume 4-17-2015 version 2 Simin Rasolee Resume 4-17-2015 version 2
Simin Rasolee Resume 4-17-2015 version 2
 
Woden/Weston Community centre Report
Woden/Weston  Community centre ReportWoden/Weston  Community centre Report
Woden/Weston Community centre Report
 
Chicago Infrastructure Trust Briefing
Chicago Infrastructure Trust BriefingChicago Infrastructure Trust Briefing
Chicago Infrastructure Trust Briefing
 
Dumbarton Crossbay
Dumbarton Crossbay Dumbarton Crossbay
Dumbarton Crossbay
 
Property Tax Assessment Financing
Property Tax Assessment FinancingProperty Tax Assessment Financing
Property Tax Assessment Financing
 
Crawfordville Town Plan Draft Report Chamber
Crawfordville Town Plan Draft Report ChamberCrawfordville Town Plan Draft Report Chamber
Crawfordville Town Plan Draft Report Chamber
 
PDCM Enterprise
PDCM EnterprisePDCM Enterprise
PDCM Enterprise
 
Single Conversation Slides 15th June 2010
Single Conversation Slides   15th June 2010Single Conversation Slides   15th June 2010
Single Conversation Slides 15th June 2010
 
Chris Kane
Chris KaneChris Kane
Chris Kane
 
2022 Federal Update from Chu Wei of the FHWA
2022 Federal Update from Chu Wei of the FHWA2022 Federal Update from Chu Wei of the FHWA
2022 Federal Update from Chu Wei of the FHWA
 
Broadway corridor-planning-program-presentation-may-2018
Broadway corridor-planning-program-presentation-may-2018Broadway corridor-planning-program-presentation-may-2018
Broadway corridor-planning-program-presentation-may-2018
 
Secrets of a Successful Land Development Approval Process
Secrets of a Successful Land Development Approval ProcessSecrets of a Successful Land Development Approval Process
Secrets of a Successful Land Development Approval Process
 
RESUME_31-Oct-16
RESUME_31-Oct-16RESUME_31-Oct-16
RESUME_31-Oct-16
 
APWA Florida Proj Award_UEP
APWA Florida Proj Award_UEPAPWA Florida Proj Award_UEP
APWA Florida Proj Award_UEP
 
Built operate transfer case studies in local construction Sector in Pakistan
Built operate transfer case studies in local construction Sector in PakistanBuilt operate transfer case studies in local construction Sector in Pakistan
Built operate transfer case studies in local construction Sector in Pakistan
 

More from Massachusetts School Building Authority (10)

Cefpi power point presentation revised
Cefpi power point presentation revisedCefpi power point presentation revised
Cefpi power point presentation revised
 
Bourne elementary and ecc timeline v2
Bourne elementary and ecc timeline v2Bourne elementary and ecc timeline v2
Bourne elementary and ecc timeline v2
 
February 9, 2011 Board Meeting, Audit Division Presentation
February 9, 2011 Board Meeting, Audit Division PresentationFebruary 9, 2011 Board Meeting, Audit Division Presentation
February 9, 2011 Board Meeting, Audit Division Presentation
 
February 9, 2011 Board Meeting, Model School Update Presentation
February 9, 2011 Board Meeting, Model School Update PresentationFebruary 9, 2011 Board Meeting, Model School Update Presentation
February 9, 2011 Board Meeting, Model School Update Presentation
 
MSBA Project Division PowerPoint, 2.9.11 Board Meeting
MSBA Project Division PowerPoint, 2.9.11 Board MeetingMSBA Project Division PowerPoint, 2.9.11 Board Meeting
MSBA Project Division PowerPoint, 2.9.11 Board Meeting
 
Board meeting presentation 11 17-10 - final
Board meeting presentation 11 17-10 - finalBoard meeting presentation 11 17-10 - final
Board meeting presentation 11 17-10 - final
 
September Board meeting Presentation
September Board meeting PresentationSeptember Board meeting Presentation
September Board meeting Presentation
 
June 2010_MACHPS_green_schools
June 2010_MACHPS_green_schoolsJune 2010_MACHPS_green_schools
June 2010_MACHPS_green_schools
 
7.28.10 Board Meeting Presentation
7.28.10 Board Meeting Presentation7.28.10 Board Meeting Presentation
7.28.10 Board Meeting Presentation
 
Mars april 2010 final
Mars april 2010 finalMars april 2010 final
Mars april 2010 final
 

September Board meeting presentation

  • 1. Board Meeting September 29, 2010 Timothy P. Cahill Katherine P. Craven Chairman, State Treasurer Executive Director
  • 2. Savings from MSBA Process Not including Bid Savings Timothy P. Cahill Katherine P. Craven Chairman, State Treasurer Executive Director
  • 3. MSBA Visits Since the July Board the MSBA has visited 43 Districts Check Presentations/ Project Visits Ground Breakings Foxborough Belmont Springfield Whitman-Hanson Littleton Malden Plymouth Woburn Taunton New Bedford Beverly Sturbridge Ashland Hingham Dartmouth Hampden-Wilbraham Wellesley Middleton Taunton Revere Haverhill Norwood Rochester Rockport Florida Hanover Braintree Revere Attleboro Quincy Marblehead Bedford Sharon Worcester Great Barrington Woburn Danvers Nashoba North Attleboro Woburn Brockton Hamilton-Wenham Palmer September 29, 2010 The Massachusetts School Building Authority 3 www.massschoolbuildings.org
  • 4. Summary of Bid Data Number of Design Basis for Project Construction Year Projects Enrollment Budget Budget 2009 11 8,188 $205.6 M $171.5 M 2010 38 30,354 $1.62 B $1.26 B 2011 9 9,270 $471.3 M $362.8 M Grand Total 58 47,812 $2.30 B $1.66 B Note: These numbers are based on preliminary information received from the District and are subject to further review and calculation. • Of the 38 projects scheduled to bid in 2010, 22 bids have been received. • To date, the bid savings for the 2010 projects is $100.3 million with potential grant savings of $57.2 million. • Sixteen projects still to be bid or GMPs finalized in 2010 with an estimated construction cost over $636 million • Bids received in September: Billerica, Natick, and Wayland • Anticipated Bids: October - Brookline, Norfolk, Danvers, Tewksbury and Dedham November - Shawsheen December - Southbridge, Grafton, Rockland, South Shore RVT, Marshfield, and Needham September 29, 2010 The Massachusetts School Building Authority 4 www.massschoolbuildings.org
  • 5. Project Estimate vs. 2010 Bid Amount Note: These numbers are based on preliminary information received from the District and are subject to further review and calculation. September 29, 2010 The Massachusetts School Building Authority 5 www.massschoolbuildings.org
  • 6. Project Estimate vs. 2009 Bid Amount Note: These numbers are based on preliminary information received from the District and are subject to further review and calculation. September 29, 2010 The Massachusetts School Building Authority 6 www.massschoolbuildings.org
  • 7. Design Development / Construction Phases Ongoing Scope, Budget & Schedule Monitoring • Total of 64 Projects: Construction Total approx $ 2.21 billion • 22 Projects in Design Development – Estimated Construction Cost of $842,747,641 • 29 Projects in Construction – Construction Cost of $1,077,265,624 • 13 Projects Completed for 2010 Occupancy – Construction Cost of $292,054,139 • 19 Additional Projects for Consideration Today – Estimated Construction Cost of $178,966,011 September 29, 2010 The Massachusetts School Building Authority 7 www.massschoolbuildings.org
  • 8. Design Development / Construction Phases Ongoing Scope, Budget & Schedule Monitoring September 29, 2010 The Massachusetts School Building Authority 8 www.massschoolbuildings.org
  • 9. Design Development / Construction Phases Ongoing Scope, Budget & Schedule Monitoring Design Development Phase Review Submittals for Design Development, 60% and 90% Review Bid Amounts and Adjust Grant Amount as Needed Track Construction Budget Throughout Design Process Using MSBA Cost Estimate Comparison Spreadsheet Scope and Budget Fixed Upon Execution of the PFA September 29, 2010 The Massachusetts School Building Authority 9 www.massschoolbuildings.org
  • 10. Cost Estimate Comparison Spreadsheet September 29, 2010 The Massachusetts School Building Authority 10 www.massschoolbuildings.org
  • 11. Design Development / Construction Phases Ongoing Scope, Budget & Schedule Monitoring Construction Phase Review OPM Monthly Reports Bi-Monthly Site Visits & Project Status Meetings Assess Eligibility of CO’s Including Owner Directives Review Reimbursement Requests Design Development Phase Review Submittals for Design Development, 60% and 90% Review Bid Amounts and Adjust Grant Amount as Needed Track Construction Budget Throughout Design Process Using MSBA Cost Estimate Comparison Spreadsheet Scope and Budget Fixed Upon Execution of the PFA September 29, 2010 The Massachusetts School Building Authority 11 www.massschoolbuildings.org
  • 12. Budget Revision Request Form Excerpts September 29, 2010 The Massachusetts School Building Authority 12 www.massschoolbuildings.org
  • 13. Vote to Move to Feasibility Study Region District Name School Name Grades Served Status Recommendation Monument Mountain Regional Feasibility Study, subject to intensive 1 Berkshire Hills 9-12 Feasibility Invitation High School pre-feasibility scoping agreement Feasibility Study, subject to intensive 4 Concord-Carlisle Concord-Carlisle High School 9-12 Feasibility Invitation pre-feasibility scoping agreement Greater New Bedford Feasibility Study, subject to intensive 6 Greater New Bedford 9-12 Feasibility Invitation Vocational Technical School pre-feasibility scoping agreement September 29, 2010 The Massachusetts School Building Authority 13 www.massschoolbuildings.org
  • 14. Green Repair Update September 29, 2010 The Massachusetts School Building Authority 14 www.massschoolbuildings.org
  • 15. Green Repair Program: FY 11 SOI Intake 200 190 • Green Repair SOI opened August 11, 2010 180 • First SOI submitted on September 2, 2010 • Green Repair SOI process closed September 22, 2010 160 • Approximately 190 SOIs under review 140 • More than 95 Districts filed SOIs • 74% SOIs submitted three days before deadline 120 # of SOI • 49% SOIs submitted on deadline 100 80 Daily Submissions Cumulative Submissions 60 40 20 0 Submittal Date 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep September 29, 2010 The Massachusetts School Building Authority 15 www.massschoolbuildings.org
  • 16. Green Repair Program Status • 39 Districts are currently in the Green Repair Program. • 12 Districts representing 23 schools were invited to participate in the Green Repair Program by the MSBA’s Board of Directors on May 26, 2010. – Of these 12 Districts, 8 have selected Owner’s Project Managers – Of these 12 Districts, 7 have selected Designers • At today’s Board meeting, MSBA staff have recommended 7 districts representing 13 schools for Project Funding Agreements totaling $9,806,692 in Total Project Budgets and approximately $5,992,870 in MSBA grants. September 29, 2010 The Massachusetts School Building Authority 16 www.massschoolbuildings.org
  • 17. Invitation to Green Repair Program September 29, 2010 The Massachusetts School Building Authority 17 www.massschoolbuildings.org
  • 18. Green Repair Program Authorization to Execute Project Funding Agreement Vote - Project Funding Agreement Total: $ 9,806,692 $ 9,620,646 $ 5,992,870 Approximate Age of District Total MSBA Total Total Grant Existing 2009/10 Existing Project Facility Grant Reimbursement Amount District School Building Grade Enroll Sq.Ft. Project Scope Budget Basis Rate Project Funding Acton CT Douglas Elementary 1965 K-6 499 46,300 $ 471,699 $ 471,699 43.85% $206,840 Agreement Project Funding Attleboro High 1961 9-12 1,756 428,700 $ 499,328 $ 499,328 57.74% $288,312 Agreement Project Funding Hill Roberts Elementary 1975 K-4 475 76,630 $ 880,000 $ 880,000 57.74% $508,112 Agreement Attleboro Project Funding Hyman Fine Elementary 1975 K-4 429 76,630 $ 880,000 $ 880,000 57.74% $508,112 Agreement Project Funding Studley Elementary 1965 K-4 432 71,000 $ 1,187,500 $ 1,187,500 57.74% $685,663 Agreement Project Funding Conway Conway Grammar School 1991 PK-6 175 31,000 $ 1,353,450 $ 1,167,404 54.36% $634,601 Agreement Goodrich School (Fitchburg Project Funding 1891 9-12 139 14,400 $ 422,714 $ 422,714 80.00% $338,171 Alternative High School) Agreement Memorial Intermediate Project Funding 1967 5-8 662 126,800 $ 1,177,532 $ 1,177,532 80.00% $942,026 School Agreement Fitchburg Reingold Elementary Project Funding 1969 K-4 574 75,900 $ 698,333 $ 698,333 80.00% $558,667 School Agreement South Street Elementary Project Funding 1963 PK-4 650 202,600 $ 701,186 $ 701,186 80.00% $560,949 School Agreement Project Funding Hancock Hancock Elementary 1958 PK-6 41 6,800 $ 277,450 $ 277,450 45.32% $125,740 Agreement Rockport Elementary Project Funding Rockport 1953 PK-5 400 65,307 $ 687,500 $ 687,500 41.10% $282,563 School Agreement Toy Town Elementary Project Funding Winchendon 1963 3-5 389 116,000 $ 570,000 $ 570,000 61.95% $353,115 School Agreement September 29, 2010 The Massachusetts School Building Authority 18 www.massschoolbuildings.org
  • 19. Recommendation to Move to Project Scope & Budget Vote - Project Scope and Budget Total: $ 217,747,744 $ 190,388,424 $ 121,637,682 Age of Proposed MSBA Total Approximate Existing 2009/10 Projected Existing Square Preferred District Total Facility Grant Reimbursement Total Grant District School Building Grade Enroll Enroll Sq.Ft. Footage Schematic Project Budget Basis Rate Amount Adams- Hoosac Valley current 7-12 77.37%, 1969 808 805 158,126 173,999 Add/Reno $40,561,257 $36,038,192 $28,243,131** Cheshire HS proposed 6-12 78.37%* Closed in 2009 Note: SOI school, however proposed solution is for the MS to remain closed and to Adams MS 1952 0 0 68,000 0 Students in HS house students in renovated HS Jr./Sr. High current 7-12 551 630 62.52%, Granby 1960 86,800 133,896 New $45,965,516 $44,562,943 $28,306,382** School proposed 6-12 (7-12) (6-12) 63.52%* current 9-12 323 Maynard High School 1962 410 82,947 121,100 New $45,769,442 $42,280,580 56.42% $23,854,703 proposed 8-12 (9-12) Medway Middle School 1960 5-8 842 800 223,780 216,820 Repair $22,116,566 $20,850,314 50.79% $10,589,875 Norfolk High School 1917 9-12 468 550 114,816 102,097 Add/Reno $28,552,385 $27,564,046 55.76% $15,369,712 County Agr East Somerville current 1-8 546 Somerville 1972 500 118,500 121,100 Add/Reno $34,782,578 $19,092,349 80.00% $15,273,879 Community proposed K-8 (1-8) *Contingent upon approval from the Office of the Inspector General to utilize CM-at-Risk construction delivery method **Approximate Total Grant Amount reflects the higher reimbursement rate. September 29, 2010 The Massachusetts School Building Authority 19 www.massschoolbuildings.org
  • 20. Adams-Cheshire – Hoosac Valley Middle/High School • Built in 1969 • Addition/Renovation: 173,999 sf • Grades: 6-12 • Category: Project Scope & Budget • District Total Project Budget: $40,561,257 • Basis of Maximum Grant Amount: $36,038,192 • Reimbursement Rate: 77.37%, 78.37%* • MSBA Maximum Grant Amount: $28,243,131** • Town Meeting Vote: October 18, 2010 • Special Ballot Vote: October 18, 2010 *Contingent upon approval from the Office of the Inspector General to utilize CM-at-Risk construction delivery method. **Based on reimbursement rate of 78.37% September 29, 2010 The Massachusetts School Building Authority 20 www.massschoolbuildings.org
  • 21. Hoosac Valley Middle/High School September 29, 2010 The Massachusetts School Building Authority 21 www.massschoolbuildings.org
  • 22. Hoosac Valley Middle/High School September 29, 2010 The Massachusetts School Building Authority 22 www.massschoolbuildings.org
  • 23. Hoosac Valley Middle/High School September 29, 2010 The Massachusetts School Building Authority 23 www.massschoolbuildings.org
  • 24. Granby Middle / High School • Built in 1960 • New Construction: 133,896 sf • Grades: current 7-12, proposed 6-12 • Category: Project Scope & Budget • District Total Project Budget: $45,965,516 • Basis of Maximum Grant Amount: $44,562,943 • Reimbursement Rate: 62.52%, 63.52%* • MSBA Maximum Grant Amount: $28,306,382** • Town Meeting Vote: October 18, 2010 • Special Ballot Vote: November 2, 2010 *Contingent upon approval from the Office of the Inspector General to utilize CM-at-Risk construction delivery method. **Based on reimbursement rate of 63.52% September 29, 2010 The Massachusetts School Building Authority 24 www.massschoolbuildings.org
  • 25. Granby Middle / High School September 29, 2010 The Massachusetts School Building Authority 25 www.massschoolbuildings.org
  • 26. Granby Middle / High School September 29, 2010 The Massachusetts School Building Authority 26 www.massschoolbuildings.org
  • 27. Granby Middle / High School September 29, 2010 The Massachusetts School Building Authority 27 www.massschoolbuildings.org
  • 28. Maynard High School • Built in 1962 • New Construction: 121,100 sf • Grades: current 9-12, proposed 8-12 • Category: Project Scope & Budget • District Total Project Budget: $45,769,442 • Basis of Maximum Grant Amount: $42,280,580 • Reimbursement Rate: 56.42% • MSBA Maximum Grant Amount: $23,854,703 • Town Meeting Vote: October 25, 2010 • Special Ballot Vote: December 2, 2010 September 29, 2010 The Massachusetts School Building Authority 28 www.massschoolbuildings.org
  • 29. Maynard High School September 29, 2010 The Massachusetts School Building Authority 29 www.massschoolbuildings.org
  • 30. Maynard High School September 29, 2010 The Massachusetts School Building Authority 30 www.massschoolbuildings.org
  • 31. Maynard High School September 29, 2010 The Massachusetts School Building Authority 31 www.massschoolbuildings.org
  • 32. Maynard High School September 29, 2010 The Massachusetts School Building Authority 32 www.massschoolbuildings.org
  • 33. Medway Middle School • Built in 1960 • Repair: 216,820 sf (excludes central admin) • Grades: 5-8 • Category: Project Scope & Budget • District Total Project Budget: $22,116,566 • Basis of Maximum Grant Amount: $20,850,314 • Reimbursement Rate: 50.79% • MSBA Maximum Grant Amount: $10,589,875 • Town Meeting Vote: November 15, 2010 • Special Ballot Vote: Based on Town Vote, 1st Week of December September 29, 2010 The Massachusetts School Building Authority 33 www.massschoolbuildings.org
  • 34. Medway Middle School September 29, 2010 The Massachusetts School Building Authority 34 www.massschoolbuildings.org
  • 35. Medway Middle School September 29, 2010 The Massachusetts School Building Authority 35 www.massschoolbuildings.org
  • 36. Norfolk County Agricultural High School • Built in 1917 • Addition/Renovation: 102,097 sf • Grades: 9-12 • Category: Project Scope & Budget • District Total Project Budget: $28,552,385 • Basis of Maximum Grant Amount: $27,564,046 • Reimbursement Rate: 55.76% • MSBA Maximum Grant Amount: $15,369,712 • Vote: October 13, 2010 • Vote: January 30, 2011 September 29, 2010 The Massachusetts School Building Authority 36 www.massschoolbuildings.org
  • 37. Norfolk County Agricultural High School September 29, 2010 The Massachusetts School Building Authority 37 www.massschoolbuildings.org
  • 38. Norfolk County Agricultural High School Agricultural Mechanics Building September 29, 2010 The Massachusetts School Building Authority 38 www.massschoolbuildings.org
  • 39. Norfolk County Agricultural High School Agricultural Mechanics Building September 29, 2010 The Massachusetts School Building Authority 39 www.massschoolbuildings.org
  • 40. Norfolk County Agricultural High School Animal Sciences Building September 29, 2010 The Massachusetts School Building Authority 40 www.massschoolbuildings.org
  • 41. Norfolk County Agricultural High School Animal Science Building September 29, 2010 The Massachusetts School Building Authority 41 www.massschoolbuildings.org
  • 42. Norfolk County Agricultural High School Annex Building September 29, 2010 The Massachusetts School Building Authority 42 www.massschoolbuildings.org
  • 43. Norfolk County Agricultural High School Horse Barn September 29, 2010 The Massachusetts School Building Authority 43 www.massschoolbuildings.org
  • 44. Somerville: East Somerville Community School • Built in 1972 • Addition/Renovation: 121,100 sf • Grades: current 1-8, proposed K-8 • Category: Project Scope & Budget • District Total Project Budget: $34,782,578 • Basis of Maximum Grant Amount: $19,092,349 • Reimbursement Rate: 80.00% • MSBA Maximum Grant Amount: $15,273,879 • City Meeting Vote: TBD • Special Ballot Vote: TBD September 29, 2010 The Massachusetts School Building Authority 44 www.massschoolbuildings.org
  • 45. Somerville: East Somerville Community School September 29, 2010 The Massachusetts School Building Authority 45 www.massschoolbuildings.org
  • 46. Somerville: East Somerville Community School September 29, 2010 The Massachusetts School Building Authority 46 www.massschoolbuildings.org
  • 47. Somerville: East Somerville Community School September 29, 2010 The Massachusetts School Building Authority 47 www.massschoolbuildings.org
  • 48. 2010 Needs Survey • Assessments – Approximately 1775 Schools – 327 School Districts • Data Accuracy – 8-week intensive QA • 20% sampling of school surveys • Queries to identify data that fell outside normal ranges • Follow-up visits to confirm data – Superintendent’s review September 29, 2010 The Massachusetts School Building Authority 48 www.massschoolbuildings.org
  • 49. 2010 Needs Survey • Scoring Methodology – Three Ratings – Building Conditions • Assessment of 7 site and 18 building systems • 1 to 4 Scale – Analogous to 2006 rating – General Physical Environment • Evaluation of conditions that affect the physical learning environment • 1 to 4 Scale – Space Utilization • How space is used compared to the average • Above Average, Average, Below Average September 29, 2010 The Massachusetts School Building Authority 49 www.massschoolbuildings.org
  • 50. 2010 Needs Survey • Condition of Massachusetts schools is good. – 80% received Building Conditions rating of 1 or 2. – Less than 2% received Building Conditions rating of 4. – 62 schools received rating of 4 in 2006. • 9 received funding • 19 in Capital Pipeline • 6 Closed September 29, 2010 The Massachusetts School Building Authority 50 www.massschoolbuildings.org
  • 51. 2010 Needs Survey • General Environment – Factors in Analysis – Daylighting – Classroom Size – Open Floor Plan • More than 90% of schools received a rating of 1 or 2 • Only 2% received a rating of 4. September 29, 2010 The Massachusetts School Building Authority 51 www.massschoolbuildings.org
  • 52. 2010 Needs Survey • Space Utilization – Factors in Analysis – GSF per student – Students per classroom – Temporary or non-traditional classrooms – Classroom size • Nearly 23% of schools received a Below Average rating • Less than 8% earned an Above Average rating September 29, 2010 The Massachusetts School Building Authority 52 www.massschoolbuildings.org
  • 53. 2010 Needs Survey • Space Utilization – Since 2006 more than 80 schools have closed or consolidated • Region 6 – 36 school closures – More than 1,300 unused classrooms • Over 1 million square feet being used for storage, district administration, municipal organizations or private entities September 29, 2010 The Massachusetts School Building Authority 53 www.massschoolbuildings.org
  • 54. 2010 Needs Survey • Maintenance – General Cleanliness – Routine Systems Maintenance – Capital Repair • 74% of schools were rated average in all categories. • Only 2% of schools received Above Average ratings in all areas • 12 schools were Below Average across the board • No relationship between maintenance and community wealth September 29, 2010 The Massachusetts School Building Authority 54 www.massschoolbuildings.org
  • 55. Project Status Report Feasibility Study / Local Schematic Design Total Clearance Design Development Construction New Program 123 35 45 21 24 Waitlist 13 2 11 Green Repair 39 12 17 1 7 Closeout/ Audit 11 Complete Total 186 47 64 22 42 September 29, 2010 The Massachusetts School Building Authority 55 www.massschoolbuildings.org
  • 56. Project Status Report • Enrollment – 2 enrollments completed this period – 9 certifications pending – Enrollments complete for projects for 66,000 students • Owner’s Project Manager – 8 districts completed OPM procurement – Over $57 million in OPM fees to date • Designer Selection Panel – 2 districts participated in DSP – 1 selection, 1 scheduled for interviews – 4 districts scheduled for DSP in October/November – Over $143 million in Designer fees • Commissioning – 2 Commissioning consultant contracts executed for $408,000 – Over $5 million in consultant contracts to date September 29, 2010 The Massachusetts School Building Authority 56 www.massschoolbuildings.org